Process Redesign to Reduce Cycle Time − A Case Study

 
 

By Dibyajyoti Bandyopadhyay

A power distribution company in India, catering to the needs of domestic, commercial, industrial and agricultural users, was not meeting the country's Electricity Regulatory Commission performance standard regulations for metering and billing. Those standards require the company to provide new power connections within 30 days from the date an application is received. In each case that the company was unable to meet the standard, it was required to pay a penalty for the delayed connection. This translated into an annual cost of 1,980,000 Rupees (US$46,000). A Six Sigma DMAIC project was initiated to reduce cycle time. This is the case study of that project.

Improvement Opportunity: The Define/Measure Phases

The project scope was limited to the process of providing new power connections to users up to a 100kw load in approved and electrified areas where the power supply network exists. The defect was defined as any new power connection that required more than 30 days to complete. Data collected for a five-month period showed an increasing trend in the number of defects with an average of 330 per month (Figure 1). Completion of the data collection plan yielded the information reflected in Table 1.

 Figure 1: Monthly Status of Pending Connections
 After Stipulated 30-Day Time Limit

Table 1: Summary Statistics of Collected Data          

 Mean

46.2

 Standard Error

1.1

 Median

 41.0

 Mode

31.0

 Standard Deviation

25.6

 Sample Variance

654.5

 Kurtosis

4.7

 Skewness

1.8

 Range

171  

 Minimum

2  

 Maximum

173  

 Sum

27328  

The project targeted benefits included cost savings associated with the amount paid in penalties, local conveyance expenditures, employee costs, and document handling as well as an increase in customer satisfaction.

Analysis and Interpretation: The Analyze Phase

A cross-functional team was formed to prepare a process map with each activity identified by one of three categories – real value-added, business value-added, non-value-added – based on the following criteria:

Real value-added included essential activities that transform inputs into outputs that are necessary to meet customer requirements and have perceived value to the customer.

Business value-added included activities that are installed by management and deemed necessary to support, control, and monitor internal business functions but have little or no perceived value to the customer.

Non-value-added included nonessential and non-processing activities that do not contribute to customer satisfaction or improved business operations.
 
The results of the analysis showed that only 19 percent of the process activities are real value-added. From a time study carried out to estimate the standard man-minutes required for performing each process activity, it was determined that the process required a maximum time of 8.2 hours. Real value-added activities comprised only 25 percent of the overall processing time (Table 2) indicating that in some stage of the process, significant breakdowns were occurring.

Table 2: Analysis of Various Activity Categories

Activity Category

Number of Activities
in Progress

Estimated Standard
Man-Hours/Case

Estimated Maximum
Man-Hours/Case

 Real Value-Adding

14

2.04

 25%

 Business Value-Adding

29

2.82

 34%

 Non-Value-Adding

31

3.31

 40%

 Total

74

8.17 

680 


To assess where significant breakdowns in the process were occurring, the total cycle time was divided into five sub-categories based on various milestone dates (Table 3).

Table 3: Definitions of Each Sub-Cycle Time

 Sub-Cycle Time  Definition
 Sub-Cycle Time-I (SCT-I)  Time between date of receipt of application and date of demand note preparation
 Sub-Cycle Time-II (SCT-II) Time between date of demand note preparation and date of printing of demand note
 Sub-Cycle Time-III (SCT-III) Time between date of printing of demand note and date of payment by customer
 Sub-Cycle Time-IV (SCT-IV)  Time between date of payment by customer and date of progress card generation
 Sub-Cycle Time-V (SCT-V) Time between date of progress card generation and date of energizing

 

 

 

 


The Pareto analysis of the sub-cycle times revealed that two cycles were accounting for 88 percent of the total time (Figure 2).

 Figure 2: Contribution of Each Sub-Cycle Time

A brainstorming session identified the significant factors affecting these times. From that information, solutions were identified.

Recommendations: The Improve Phase

To redesign the process all non-value-added activities were eliminated, business value-added activities were minimized, and real value-added activities were streamlined. Key improvements included the following:

  • The application form and agreement form were combined, reducing the number of required documents and eliminating duplicate information.
  • Databases related to meter reading status and bill payment status of existing customers were made accessible online to detect potential status issues before accepting the application. Detection at the application receiving stage rather than at a later stage helped reduce rework and improve customer satisfaction.
  • Systematic calculations of charges and implementation of an e-mail messaging system for communication of potential issues made the process flow faster and be less prone to errors.

The redesigned process was piloted in one district during a four-week period. A time study was carried out to estimate the standard man-minutes required for performing each activity in the new process (Table 4). Results were positive, with the new standard deviation set at 4.8 days and the mean total cycle time reflecting 12.1 days, a substantial reduction over the previous process mean of 46.2 days. In addition, the number of activities in the process was reduced from 74 to 36.

Table 4: Analysis of Various Activity Categories

Activity Category

Number of Activities
in Progress

Estimated Standard
Man-Hours/Case

Estimated Maxium
Man-Hours/Case

 Real Value-Adding

9

1.7

 32.7%

 Business Value-Adding

27

3.5

 67.3%

 Non-Value-Adding

  0

0.0

   0.0%

 Total

36

5.2 

100.0% 


At Last: The Control Phase

To monitor and control ongoing process performance, the company implemented a database to track each application and monitor the key sub-cycles. A concise reporting format also was developed to track the weekly progress of energizing within each zone and the overall performance for each district.

A cost-benefit analysis conducted after full implementation of the new process in all zones quantified the net savings for the company (Table 5) and confirmed the success of the project.

Table 5: Cost-Benefit Analysis

 Account Headings

Amount (Rupees)

 Remarks
   Savings/per annum from:
   Penalty money
   Expenditure on local conveyance 
 
       1,980,000
       1,008,000 
 
 Based on past performance
 Based on data provided by the claimants
   Total Annual Savings       2,988,000  
   Expenditure per annum for:
   Purchase of two mobile 
       supply vans
       (one for each five districts)
   E-mail costs (2,000 Rupees per
       month per zone)


          160,000
 
 
          960,000
 


 Based on cost of vans totaling 800,000 Rupees amortized
   over five years. Annualized cost 160,000 (Maintenance
   cost of vans was not considered)
 Approximated
 

   Total Annual Expenditures       1,120,000 
 Total Net Annual Savings       1,868,000 

About the Author

Dibyajyoti Bandyopadhyay has been a consultant and trainer in Six Sigma and Quality Management System (ISO 9000, QS 9000) for eight years. His experience includes program implementation, process management, manpower planning, organization restructuring, production system design, modernization and technology upgrading. He has assisted many organizations in implementing ISO 9000 QMS. He has rendered consulting services to companies like Hindustan Electro Graphites, Indorama Synthetics (I) Ltd., Fujitsu Optel Ltd., Tata Power, Department of Telecommunications. He can be reached at dibyajyotib@hotmail.com.

 

Best Selling Products

  1. Certified Lean Six Sigma Green Belt Assessment Exam
    This assessment exam is useful for students interested in assessing their knowledge of Lean Six Sigma on the Green Belt ...
  2. Certified Lean Six Sigma Black Belt Assessment Exam
    Interested in assessing your knowledge of Lean Six Sigma? Preparing for certifications? Testing your students and traine...
  3. 5S Training Course
    One of the key fundamental tools of process improvement is 5S. 5S is a methodology for organizing and minimizing item...
  4. Six Sigma Black Belt (DMAIC) Training Slides
    The 2008 Six Sigma Black Belt course is comprised of: 1,176 PowerPoint slides, Instructor notes, Slide explanations, 37 ...
  5. Six Sigma DMAIC Training Slides
    The complete 2008 Lean Six Sigma DMAIC course prepares participants to perform the role of a LSS Black Belt; covering wh...
  6. Gage R&R Excel Template
    Gage Repeatability and Reproducibility (R&R) studies measure the amount of measurement variation that is attributabl...
  7. CSSBB Preparation Pack
    The CSSBB Preparation Pack includes materials for passing the Certified Six Sigma Black Belt (CSSBB) exam. This CSSBB Pr...

Premium Sponsor:

Accenture, Process & Improvement Performance, formerly George Group

Sponsors:

Achieve Operational Excellence: STAT-A-MATRIX

Advance your Military Career with Six Sigma Programs from Villanova University

MoreSteam: The Engine Room of Continuous Improvement

Novaces: Six Sigma for the Military

Sponsor iSixSigma Military



 

About iSixSigma Military

The purpose of this iSixSigma Military channel is to document the transformation of the United States Armed Services through the use of Lean Six Sigma and related process improvement methodologies.

Ronald E. Rezek, special assistant to the acting secretary of the Army, has said the goal of the Army's Lean Six Sigma deployment is to "make the business side of the Army as efficient as the war-fighting side is effective." Leaders of the other armed services echo that sentiment and transformation objective.

This portal will serve as a central community for everyone associated with the business transformation of the U.S. military. It will provide communication updates on deployments, the opportunity for military leaders at all levels to learn new skills, advance their careers and contribute to the success of their organizations.